WORKPLAN

 

 

 

DELIVERABLES LIST

Deliv Nr
Deliverable name
WP no. (1)
Nature (2)
Dissem.
level (3)
Delivery
date (4)

D1.1 Database of Regional/National RTD Policy Makers in the ICT & Agri-food domain and list of network nodes from RTD projects
WP1
R
PU
M3
D1.2 Information exchange model design
WP1
R/O
RE
M3
D1.3 Questionnaires and web based questionnaires and description of on-the-field activities. link
WP1
O/R
PU
M5
D2.1 Identification of RTD strategies in the target regions and data validation. link
WP2
R
PU
M9
D2.2 Inventory of identified constraints by sector (EU relevant, current and future legal, regulatory and standards). link
WP2
R
RE
M12
D3.1 Common Basis for Policy making for introduction of innovative approaches of Collaborative working in Agri-food industry (Draft Roadmap). Download link
WP3
R
RE
M10
D3.2 Consensus report resulting from Roadmap validation process & Common Policy Statement.
WP3
R
RE
M13
D3.3 Rough proposal for TP for the 7th FP
WP3
R
PU
M15
D4.1 Dissemination & Networking strategy.
WP4
R
PU
M3
D4.2.1 Dissemination & Networking plan as the first version of the PUDK. Impact indicators.List of proposal for Joint Activities.
WP4
R
PU
M3
D4.2.2 Final version of PUDK and dissemination evaluation report
WP4
R / O
RE
M15
D4.3 Dissemination material
WP4
R / O
PU
M3-M15
D5.1 Self Assessment procedures and Indicators
WP5
R
RE
M3
D5.2.1_2 6, 12 Month Progress Reports
WP5
R
PU
M6, M12
D5.3 Project Presentation
WP5
R
RE
M6
D5.4 Final report
WP5
R
PU
M15
D5.5 Final report for publication.
WP5
R
PU
M15
  1. Deliverable number: D1 - Dn
  2. R= Report / P= Prototype / D= Demonstrator / O= Other
  3. PU= Public / PP= Restricted to other programme participants (including the Commission Services) /
    RE= Restricted to a group specified by the consortium (including the Commission Services) /
    CO= Confidential, only for members of the consortium (including the Commission Services)
  4. Month in which the deliverables will be available. Month 0 marking the start of the project, and all delivery dates being relative to this start date.

WORKPACKAGE LIST

Work Package No (1)

Work package title Lead contractor (2) Start Month (3) End Month (3) Deliverable No (5)
WP1 Establish Network & Information exchange platform INNOPOLE
M1
M5
D1.1 D1.2 D1.3
WP2 Data collect. & Analysis of Regional, National RTD strategies. Tech. Independent ATB
M3
  D2.1 D2.2
WP3 Create Consensus on Regional Strategies for Collaborative Working in Agrifood networked businesses NYHERJI
M6
  D3.1 D3.2 D3.3
WP4 Dissemination & Networking INNOPOLE
M1
M15
D4.1 D4.2.1-2 D4.3
WP5 Project Management INNOPOLE
M1
M15
D5.1 D5.2.1-2 D5.3 D5.4
  1. Deliverable number: D1 - Dn
  2. Name of the contractor leading the work in this work package.
  3. Relative end date, month 0 marking the start of the project, and all ends dates being relative to this start date.
  4. Deliverable number: Number for the deliverable(s)/result(s) mentioned in the work package: D1 - Dn.

 

© Copyright Ami-netfood Consortium 2005